800–3000 kW medium-voltage mobile power units

800 kW is a genuine dividing line in mobile supply — not because large sets are hard to build, but because at 400 V the cable becomes too heavy to reel, the reel too large to fit, and the volt drop too high for the load at the far end. At medium voltage the same power is tens of amps and a single cable the thickness of a finger carries it 100 m. The price is a transformer, switchgear, protection settings and a set of type tests.

Short answer: above 800 kW, go to 6.6 kV or 11 kV. Three routes: ① LV set plus step-up transformer (most common, cheapest set, costs floor space); ② MV alternator generating directly (no transformer, 15–25% dearer); ③ several LV sets paralleled into one step-up unit. Protection settings, neutral earthing and cable terminations must all be redone to MV practice — an LV unit cannot simply be scaled up.

Yellow MV power vehicle on a semi-trailer: tractor unit with four-axle trailer, louvred intake and exhaust panels along the body
Above 800 kW there are two common formats: the container craned into position (roof or plinth, load spread, no vehicle type approval) and the semi-trailer vehicle. This one is the semi-trailer: tractor unit plus a four-axle trailer, louvred intake and exhaust panels and service doors along the body — the right choice for work that moves between regions and for distribution bypass. The trade-off is vehicle type approval, plus towing and braking to semi-trailer rules.

Why 800 kW: the current calculation

Rating400 V full-load current400 V cable / mass per 100 m10.5 kV current10.5 kV cable / mass per 100 m
400 kW~722 A2×185 mm² / ~660 kg~25 A25 mm² / ~30 kg
800 kW~1,155 A3×240 mm² / ~1,300 kg~50 A35 mm² / ~42 kg
1,200 kW~1,732 A4×240 mm² doubled / ~3,400 kg~75 A35 mm² / ~42 kg
2,000 kW~2,887 Ano practical arrangement~125 A50 mm² / ~60 kg

At 1,200 kW the LV route needs eight 240 mm² cores in parallel: 3.4 tonnes of copper and a reel over 2 m in diameter. That is not a question of cost — the cable physically will not fit on a vehicle and will not be dragged across a site. At 10.5 kV the same 1,200 kW travels on one 35 mm² core weighing 42 kg.

Three technical routes

RouteAdvantagePenaltyBest for
LV set + step-up transformerStandard set, cheap, spares everywhere, any mechanic can service itTransformer takes 2–4 m² and 1.5–3 t; one extra 1.5–2% loss800–2,000 kW, most projects
MV alternator, direct generationNo transformer, one less loss (~1.5%), body 2 m shorterSet costs 15–25% more, high insulation class, fewer models availableAbove 1,500 kW, or length-limited
Multiple LV sets into one step-up unitSmaller individual sets, easier transport, N+1 availabilityParalleling and protection coordination, longer commissioning2,000–3,000 kW, redundancy required

Switchgear and protection: do not copy LV settings

Islanded MV generation is not grid supply. Fault current comes from the set itself and is limited, so the settings logic is different:

If the unit will run in parallel with the utility, obtain the connection agreement first — protection settings, earthing method and metering point are all approved by the utility, typically 4–8 weeks. That is the hidden critical path in most MV projects.

Neutral earthing: three options

MethodFault currentAdvantageCost and use
UnearthedCapacitive only, usually <10 ASupply continues; an earth fault can run for 2 hoursNeeds insulation monitoring; arcing over-voltage risk with long cable
Arc-suppression coil<10 A residual after tuningSuppresses arcing over-voltage, suits cable networksTuning follows network changes — awkward on a mobile unit
Low resistanceTypically 100–400 ADefinite settings, reliable tripping, limits over-voltageTrips on the first earth fault; usual choice for mobile MV

A mobile unit's cable length changes with every deployment, so capacitive current cannot be known in advance. Low-resistance earthing is the robust answer: fixed settings, reliable protection, independent of cable length. It trips on a single earth fault — which is the right trade for emergency supply.

MV cable reel: three details people miss

Practical note: lock the reel during transport and keep it dry. A damp termination will flash over in eight out of ten withstand tests, and re-terminating on site costs three to four days.

Four tests before delivery

TestAcceptanceTypical failure cause
Insulation resistance2,500 V tester, ≥1,000 MΩMoisture, contaminated termination
Power-frequency withstand28 kV / 1 min for 10.5 kV equipment (or 0.8× works value)Termination defect, insufficient clearance
Partial discharge≤10 pC at 1.2× phase voltageBusbar burrs, contaminated support insulators
Protection setting verificationInject and confirm every element against the setting sheetWrong CT ratio, superseded setting sheet

All four belong in the works test report; on site you only re-verify. Finding an MV defect after delivery costs far more than the equipment.

Paralleling and distribution switchgear with breakers, metering and protection
Paralleling and distribution panels. On the MV side, CTs, VTs, interlocks and voltage presence indicators are all part of the utility acceptance.
Containerised generator set craned onto a roof slab
Containerised MV set: intake, exhaust, silencer and switchgear all built in, so on site you make one cable connection.

Price and lead time

Capacity and routeIndicative FOB ChinaLead timeTypical duty
800–1,100 kW, LV set + step-upUSD 125,000–195,00090–110 daysCity distribution standby, substation support
1,100–1,500 kW, MV alternatorUSD 208,000–305,000100–120 daysMajor events, rail, airports
1,500–2,000 kW, multi-set + step-upUSD 278,000–390,000110–130 daysRegional emergency depots, industrial parks
2,000–3,000 kW, semi-trailer or multi-boxUSD 390,000–585,000120–150 daysNational response fleets, black start

Cost mix is very different from LV: the set is only 40–50%, transformer/switchgear/protection 20–30%, body and trailer 15–20%, cable and reel 8–12%. Two quotes for the same 1,000 kW can differ by USD 30,000 purely on switchgear configuration — one incoming or two, single or duplicate protection.

Indicative FOB China references excluding freight, duties, connection studies and craning. Export configurations must state the destination voltage (11 kV / 13.8 kV / 33 kV) and the applicable standard (IEC or ANSI).

Questions buyers actually ask

Is medium voltage mandatory above 800 kW?

Not mandatory, but marginal. At 800 kW and 400 V the current is 1,155 A, needing 3×240 mm² and 1.3 t of copper per 100 m. With a 30 m reel and a fixed site LV still works; at 100 m MV is the better answer.

LV set with a transformer, or an MV alternator?

Below 1,500 kW take the step-up route: cheaper set, common spares, easier servicing. Above 1,500 kW, or when body length is constrained, the MV alternator earns its 15–25% premium by removing the transformer and one loss stage.

How should the neutral be earthed?

Low resistance for mobile MV: fixed settings, reliable protection, independent of cable length. Fault current typically 100–400 A, tripping on the first earth fault.

Can an MV unit run in parallel with the grid?

Yes, but obtain the utility's connection agreement first. Protection settings, earthing and metering point are approved by them, typically 4–8 weeks.

Why can the MV reel not be extended on site?

MV terminations are cold- or heat-shrink and need controlled conditions. Reel length is fixed at works with pre-made terminations; on site you can only connect pre-terminated joints.

Why is lead time over 100 days?

Set 35–45 days, transformer 30–40, switchgear 30–45 — in parallel still more than 60 days, plus integration, withstand and PD testing, and transport. Add 4–8 weeks if a utility connection study is required.

Fix the connection method before discussing price

Send the capacity, the required voltage (6.6 / 11 / 13.8 kV), whether it parallels the grid, cable length and transport constraints. You get a route recommendation, switchgear configuration and a price range.

Call +86 135 1772 8899 Email us

Related: Mobile power units 20–3000 kW · 20–200 kW pickup & light truck · 200–500 kW truck-mounted · Containerised generators · Export process · Hospital standby · Data centre · Events · Emergency response