Hospital backup power: sizing a mobile generator for theatres, ICU and fire loads
Most hospitals already have a standby diesel set and a UPS layer, so a mobile unit is not "power from zero" — it covers the gap when the fixed set fails, goes into overhaul, runs out of fuel, or while a new wing is still being commissioned. Once you fix that role, the rating stops being a multiple of the transformer size, and the connection point stops being a guess.
Short answer: a 400–600 bed general hospital needs a 200–500 kW mobile unit to carry theatres, ICU, blood bank, medical lifts and fire loads — not a unit sized on a 1,250 kVA transformer. The number that matters is the actual kW of critical + fire load, typically 25–35% of installed capacity. Uninterrupted power for theatres and ICU is the UPS's job; the vehicle takes over once the battery string has done its part.
Divide the load into tiers before talking about kW
Hospital distribution is already prioritised. The vehicle does not carry the campus; it carries the part that cannot stop. In practice that means three decisions: what to carry, for how long, and who closes the switch.
| Load tier | Typical equipment | Share of load | Allowed interruption | Vehicle carries? |
|---|---|---|---|---|
| Vital | Theatres, ICU/NICU, delivery, blood bank, DSA, network room | 20–30% | 0 (UPS / isolation supply) | Yes, after the battery string |
| Fire | Fire pumps, sprinkler, smoke extract, fire lifts, escape lighting | 10–15% | ≤15 s | Yes, first priority |
| Essential | Medical lifts, laboratory, imaging, oxygen plant, water pumps | 20–25% | ≤30 s | Depending on capacity |
| General | HVAC, lighting, kitchen, laundry, offices | 35–45% | 1–2 h acceptable | Normally no |
The important use of this table is to strip general load before sizing. A campus quoted at "2,000 kW installed" often has half of it in chillers and lighting; sizing on that number costs an extra USD 100,000 and produces a vehicle that cannot get through the gate.
Sizing: bed-count and transformer rules both mislead
| Beds | Transformers | Critical + fire load | Recommended unit | Connection |
|---|---|---|---|---|
| 200 (county) | 2 × 800 kVA | 180–250 kW | 200–250 kW | Spare breaker, LV room |
| 400 (city) | 2 × 1,250 kVA | 280–380 kW | 300–400 kW | Spare breaker + rapid connection box |
| 600 (tertiary) | 3 × 1,250 kVA | 400–520 kW | 400–500 kW | Rapid connection box (400/630 A) |
| 800+ | 2 × 1,600 kVA and up | 550–750 kW | 630–800 kW | 10 kV mobile substation or MV vehicle |
One exception needs its own calculation: imaging. A 3.0 T MRI gradient coil can draw 3–4× its rated current during sequence switching, and CT tubes and linear accelerators behave in the same family. If the vehicle carries that load directly, size on steady state plus the step, and preferably keep the imager behind a UPS or its own feeder.
Connection: three ways, and only one avoids an outage
| Method | What it involves | Outage needed | When it fits |
|---|---|---|---|
| Spare breaker in LV room | Cable onto a reserved breaker, open the bus coupler, feed one section | 5–15 min | Spare way exists and a section can be dropped briefly |
| Rapid connection box | Fixed 400/630 A socket on the wall, mechanically interlocked with mains | None, connect in 10 min | New build or a hospital refurbished in the last five years |
| Mobile substation / MV unit | 10 kV into a spare ring-main way, step down to 400 V | 20–30 min | Above 800 kW, or no LV cable route |
- The cable route fails before the cable does. Basement clearance, ramp radius, fire shutters and loading docks decide whether a 185 mm² drum can get in at all. Walk the vehicle route before agreeing a scheme.
- Earthing and polarity. Hospital LV systems are usually TN-S; the vehicle neutral must be solidly earthed at ≤4 Ω. A theatre isolation transformer (IT system) cannot be replaced by the vehicle — it exists to survive a first insulation fault, not to supply power.
- Back-feed interlock. Mechanical plus electrical interlock between mains and vehicle incomers, no exceptions. Back-feeding a hospital network puts maintenance staff directly in contact with live conductors.
Switching time and UPS: who covers which minute
Theatre and ICU battery strings typically hold 15–30 minutes — enough for the fixed set to start and the ATS to transfer. If the fixed set does not start, a vehicle takes 40–90 minutes to arrive and connect in a city. The real risk is therefore not "do we have a vehicle", it is "does the battery string survive the gap".
Three practical consequences: recalculate UPS autonomy on the actual load (a five-year-old string often delivers only 60% of nameplate); install the connection point before you need it; and write "connect the mobile generator" into the hospital's emergency drill script as a formal step, not an improvisation.
Targets: fire loads ≤15 s, essential loads ≤30 s, theatres and ICU 0 s — the zero comes from the UPS, not from the generator. Any claim that a vehicle delivers "zero-transfer" power deserves the question "through what".
Harmonics, exhaust and noise: three hospital-specific constraints
- Harmonics. CT, MRI, DSA, inverter chillers and LED lighting together commonly produce 25–35% THDi. A synchronous set tolerates far less than a transformer because the losses land in the stator and exciter windings: derate to 0.85 as standard, 0.8 above 30% THDi.
- Exhaust. Never toward ward windows, fresh-air intakes or the outpatient entrance — keep 10 m horizontal clearance, or run a temporary flue to roof level. This is the most-complained-about item at handover and the hardest to retrofit.
- Noise. Site boundaries at night are usually limited to 55 dB(A); a canopied set is 65–70 dB(A) at 7 m. Use distance (6 dB per doubling), an acoustic barrier, or the lee side of a building. Below a ward block, barrier plus low-speed running is usually the only workable combination.
- Fuel. No open flame or temporary tank inside the campus. Carry eight hours on board and refuel from a tanker outside the perimeter, on a route that does not block the fire lane.
Acceptance: three tests, all recorded
| Test | Method | Pass criterion |
|---|---|---|
| Load test | Resistive load 100% for 2 h, then 110% for 1 h | Stable water, oil and exhaust temperature; no derate, no trip |
| Transfer drill | At least twice, one at night, with a real mains interruption | Fire loads back within 15 s, essential within 30 s, UPS stays on inverter |
| Endurance and refuelling | Run to low-fuel alarm at full load; practise a refuel | ≥8 h; refuel completed within 30 min |
Questions hospitals actually ask
We already have a standby generator — why a vehicle?
Different failure. The fixed set answers "what if mains fails"; the vehicle answers "what if the fixed set fails" — breakdown, major overhaul, fuel contamination, or a capacity gap during expansion. Tertiary hospitals also use one for months while a new wing is commissioned.
Can the vehicle feed a theatre directly?
No. A theatre is protected by a UPS and an isolation transformer; the vehicle feeds the UPS input so the battery is not drained. A direct cable into a theatre is both non-compliant and destroys the IT-system insulation monitoring.
What size for a 400-bed hospital?
300–400 kW covers critical and fire loads. The precise figure comes from the hospital's load calculation and the size of the imaging department; we do not recommend sizing on transformer capacity.
Does connection require a mains outage?
With a rapid connection box, no — only the bus coupler is opened. Only the spare-breaker method needs a 5–15 minute outage, which is why fitting a connection box during construction is the best-value item in the project.
Can we park a fuel tank on site?
Rarely. Hospitals are assembly occupancies and temporary fuel storage needs fire approval. Eight hours on board plus a tanker outside the perimeter is the normal arrangement.
Will the noise reach the wards?
Yes, and it is the most common complaint. 65–70 dB(A) at 7 m against a 45 dB(A) night limit at a ward façade cannot be solved by insulation alone — position and barriers do the work.