Containerized diesel generators: when the whole power plant ships in a box
Above roughly 500 kVA, a genset stops being a machine and becomes a small building — it needs switchgear, a fuel system, ventilation, fire detection and a place to put all of it. A containerised module delivers that as one tested unit that a crane can set down in an afternoon.
What actually ships inside the container
The genset is the obvious part. The rest is what determines whether commissioning takes two days or two weeks.
- Genset on a common base frame — engine, alternator, radiator and couplings aligned and dowelled at the factory, not on site.
- Control and switchgear — controller, breaker, metering, protection relays and, where specified, the paralleling panel for multi-set operation, mounted in an air-conditioned compartment at the cool end of the container.
- Base fuel tank — typically 8–24 hours at 75 % load, bunded, with fill point, vent, level gauge and leak detection accessible from outside.
- Ventilation system — inlet and outlet attenuators sized to the radiator airflow, with motorised dampers that close on shutdown to keep the acoustic rating and exclude rain and dust.
- Exhaust system — critical-grade muffler inside the shell, tailpipe through a wall gland, with a flexible section to isolate vibration from the structure.
- Fire detection and suppression — heat and smoke detection as standard; clean-agent or aerosol suppression where the client's insurer requires it. Never CO₂ in an occupied compartment.
- Lighting, sockets and a small workbench — the details that make night-time servicing possible.
Sizing: which container for which rating
| Shell | Typical rating | Internal layout | Gross weight |
|---|---|---|---|
| 10 ft | 200–350 kVA | Single compartment, tank in base | 4.5–6.5 t |
| 20 ft | 400–1000 kVA | Genset room + switchgear room | 9–14 t |
| 20 ft high cube | 800–1250 kVA | Taller shell for large radiators and top-mounted exhaust | 12–16 t |
| 40 ft | 1250–2500 kVA (single) or 2 × 1000 kVA | Two compartments, walk-in service aisle | 22–32 t |
| 40 ft high cube, twin | 2 × 1500–2000 kVA, N+1 | Two sets, common switchgear, shared tank | 30–38 t |
Weight matters more than size for shipping. A 40 ft twin module at 35 t exceeds many road limits and needs a low-bed trailer plus permits in most countries. Confirm the route from port to site before agreeing the configuration — the cheapest module is not cheap if it cannot reach the site.
Paralleling and N+1: decide before the shell is built
Adding a second set to a single-set module later means replacing the switchgear, re-running busbars and re-certifying the protection scheme — usually 40–60 % of the original module cost. If there is any chance you will need redundancy, order the paralleling-ready configuration at the start: a busbar with a spare outgoing section, a controller that supports load sharing, and space in the switchgear compartment.
| Configuration | What it gives you | When it is worth it |
|---|---|---|
| Single set | Simple, lowest cost | Standby duty where a short outage is tolerable |
| Paralleling-ready single | Add a second set later without rebuilding switchgear | Load likely to grow within 3 years |
| 2 × 50 % with load sharing | One set carries the load if the other fails | Hospitals, data rooms, process plant |
| N+1 (2 × 100 % or 3 × 50 %) | Full redundancy with maintenance without outage | Data centres, telecom hubs, continuous process |
Medium voltage changes everything
Above about 1250 kVA, generating at 400 V means thousands of amps and busbars the size of your arm. Generating at 6.6 kV or 11 kV and stepping down at the point of use is usually cheaper and always easier to cable. A medium-voltage module adds a step-up transformer, MV switchgear and MV protection — and it changes who can work on the unit, because MV switching needs authorised personnel, not a mechanical technician.
Transport and lifting
- Corner castings to ISO 1161 so the module is handled like any container — no special lifting frame.
- Lift points marked and rated, with a lifting plan issued for anything above 25 t.
- Fork pockets are useful under 12 t and misleading above it; do not assume a 20 t forklift is available on site.
- Sea fastening for the genset and switchgear inside the shell — the set must be blocked and braced for a sea voyage, not just bolted to the base frame.
- Shipping position of dampers, exhaust cap and door locks documented in the unloading instructions, or the first rainstorm floods the control compartment.
Where containerised beats a silent canopy
Choose the container when: the rating is above 800 kVA, you need walk-in access for service, you want switchgear and fuel in the same delivery, the site needs a stackable or relocatable asset, or the project requires a documented fire-protection scheme. Choose a skid-mounted silent canopy when the set is under 500 kVA, access is tight, weight is a constraint, or the client simply wants the lowest installed cost.
Send the load list and the site plan
Tell us the rating, voltage, required autonomy, redundancy level and the route from port to site. We return a module layout, a single-line diagram and a firm price — within two working hours.
Request a quotation See price guideQuestions buyers ask
Can a containerised module be installed outdoors in hot climate?
Yes, and it is the normal case. The design ambient is usually 40 °C; above that, the set is derated and the ventilation fans are upsized. What matters is that the discharge air is not trapped — allow at least 3 m clear in front of the outlet and never place two modules outlet-to-outlet.
Is the container CSC-plated and certified for sea transport?
The shell is built to ISO dimensions and corner castings, and can be CSC-plated on request. Note that a genset module is not a freight container and will not usually be stacked in a container stack at sea — it ships as break-bulk or on flat rack, which affects freight cost.
How long does commissioning take on site?
Two to four days for a single module including offloading, positioning, cable termination, fuel filling, protection checks and a stepped load test. Twin modules with paralleling take five to seven days, because load sharing and protection coordination have to be proved at every step.
What fire protection is normally specified?
Heat and smoke detection with alarm to the site system is the baseline. Insurers commonly require clean-agent or aerosol suppression inside the genset compartment, plus fire-rated separation from the switchgear compartment. We build to the client's fire scheme; we do not substitute our own.